Wiring diagram




The procedure of technological connection of power-receiving devices of legal entities and individual entrepreneurs with the capacity up to 100 kw by one power source passes on the following stages:

1. Preparation of topographic survey from the point of accession to the boundary of the land plot of the applicant. is carried out with the involvement of third party organizations. Term of execution – no more than 10 working days;

2. Departure to the place for selection of the route of passing of the transmission line (place of TP installation). Term of execution – no more than 2 working days;

3. Development of project documentation to the boundary of the applicant's land plot. is carried out after submission of the project documentation by the applicant within the boundaries of the site. Term of execution – no more than 10 working days;




4. Coordination of project documentation with interested organizations. Term of execution – no more than 5 working days;

5. Coordination of project documentation with owners of land plots, on which the route of the transmission line (or place of installation of TP) passes. Term of execution – no more than 7 working days;

6. Coordination of project documentation with the Committee of Architecture and Urban planning. Term of execution – no more than 10 working days;





7. Development of the estimated documentation for the agreed project. Term of execution – no more than 5 working days;

8. Conclusion of contract and (or) contract for supply of equipment and materials. is carried out in accordance with the requirements of the Federal law of July 18, 2011 № 23-FZ "on procurement of goods, works, services by certain types of legal entities". Term of execution – no more than 14 working days;

9. Execution of wiring works on the laying of power lines (installation of TP) from existing electrical networks to the boundary of the land plot of the applicant. Term of execution – no more than 15 working days;

10. Verification of the applicant's compliance with the technical conditions of departure to the place. Term of execution – no more than 1 working day;

11. Registration of the certificate of compliance with technical conditions. Term of execution – no more than 1 working day;

12. Realization of actual connection of objects of the applicant to electric networks and inclusion of the switching apparatus under the tension with registration of the Act on technological accession. Term of execution – no more than 3 working days.

The total procedure of technological connection of the receiving devices is not more than 83 days. These terms are indicative, as in each individual case the technological connection is individual in nature.